Boiler Control Panel Upgrade & System Optimisation

To address obsolescence and improve efficiency, two modern control panels were installed on existing 150 PSI, 9000 kg/hr steam boilers. This upgrade replaced outdated and redundant controls, significantly improving system reliability and visibility.
 

The new panels, equipped with oxygen (O₂) trim sensors, enabled tighter combustion control, resulting in notable fuel savings. The strong return on investment made the project easy to sponsor.
 

As part of the wider optimisation effort, nearby steam traps were replaced, and steam lines were re-lagged to further improve system efficiency. Boiler water chemistry was also assessed and confirmed to be working optimally.
 

Future opportunities: additional savings have been identified, including insulating the boiler house to reduce heat loss and further cut energy use.

Savings

Client Testimonials

"From understanding legal requirements of ESOS and EED the professional was able to design, instruct and have 42 reports completed across the EU and UK. The regulators confirmed the company was in compliance. The board was then able to prioritise necessary investment."

Christina Stapis, DNV Ltd.


"We've partnered on countless successful projects with great collaboration, consistently strong technical contributions, and drive to get projects over the finishing line. The outcomes have been a testament to the power of teamwork and execution. We look forward to our next project."

Anthony Marshall, ECAD Engineering Ltd.

Gallery

bottom of page